Time and
Physical Demands Analysis
By Dan MacLeod CPE
www.danmacleod.com
June 19, 2007

Time and
Physical Demands Analysis combines biomechanics with time study
and is the most practical approach to quantitative analysis that I
have found. The original concept for this method was developed
by Peter Holzmann, Ph.D., based on his own
proprietary scoring system, which I found too complicated for
practical use. I subsequently tried the Rapid Upper Limb Assessment (RULA)
scoring system,
then realized that biomechanics provided an even better approach to
characterizing physical demands for this purpose.
The method
is valuable for a number of reasons:
-
It shows
the physical demands for each step of a job, enabling you to see
more clearly where the problems.
-
It
includes time in a way that most other methods do not,
enabling you to see how ergo problems usually take longer and
interfere with efficiency.
-
The
graphs are easily understandable by managers and decision-makers,
providing you a good format around which to base a report or
presentation.
-
Using
biomechanics as the foundation of the method bypasses many arguments
on how to combine the effect of different Musculoskeletal Disorder (MSD) risk factors, thus
makes the results more scientifically accurate than other common
measurement systems.
-
The
results are intuitive, i.e., the load on the shoulder measured in
pounds or foot pounds (or Newton-meters in the metric system).
-
The
method includes most of the key variables of concern:
-
Posture
-
Force
-
Motions
(each motion is separately observable on the graph)
-
Magnitude of the load on the body
-
Duration of the load on the body
I have
found the Time and Physical Demands Analysis is especially good
in making before-and-after comparisons, in particular since it often
shows how reducing the physical demands of a task reduce time
requirements. Note that it is helpful for studying jobs that
involve full arm motions and bending of the back, although it is not
yet fully applicable for the hand or fine movements of the forearm.
The method
involves the following steps: videotape the task; review the video
pausing each 0.5 second, calculate the loads on the shoulder and back
for that frame using standard biomechanical models (in these examples,
the Utah models), and graph the results.
Example 1: Wasted time and back
strain
The
following photos are taken from a video clip of one cycle of a packing
job. Each photo shows one of the four primary steps of the task,
which involved picking up products from a pallet on the floor, then
placing them in three shipping boxes. The arrows show the
corresponding section of the graph (the graph was generated from a
full video clip; these photos are simply to help you see what the
graphs depict.)

The full
work cycle for this task took 23.5 seconds, as shown on the horizontal
axes of the two graphs. The loads on the arms and back are shown on
the vertical axes, thus the higher the peak and the larger the area
under the curve, the greater the strain.
Bending
over to lift the product from the pallet (3.5 seconds) is very
observable in the Back graph, as would be expected.
Carrying
the products to the conveyor (2.5 seconds) places a relatively small
load on the back since the employee is now erect. The load on the
arms increases somewhat because the products are large, causing the
arms to be more extended than when bending and lifting.
The next
step is placing the products on the conveyor (4.5 seconds). Since the
weight of the products now primarily rests on the conveyor, the loads
on the body are reduced.
Placing the
products in three boxes (10 seconds) results in three blips on the
graphs, as the arms are extended with the weight of the product in
order to put it into the box.
The final
step (3 seconds) is simply walking back to the pallet to start another
cycle. No photo is shown of this step, but the absence of any load
other than the weight of the upper torso is clearly depicted on the
graph.
The graph
for the Back shows the issues most dramatically. Clearly the strain
on the back is associated with bending down to the pallet to lift the
product.
Most people
who are involved with ergonomics would understand this point without
needing to conduct a study. However, it can be helpful to show
managers and engineers this type of graph because it is easy to
understand and the problems sort of point themselves out.
More
importantly, the graph shows the time involved. Packing the boxes
(the only value-added step) took 10 seconds. The remaining 13.5
seconds (57% of the work cycle) were wasted activities like walking
and carrying. If a pallet lift were used and moved adjacent to the
conveyor, the wasted time would be eliminated along with unnecessary
physical demands. In fact, if set up properly, the employee could
load two different products with less effort and less risk of injury
than the current method.
Example 2: Time Savings from a
Pallet Lift
This
example from a distribution center shows how a standard pallet lift
reduced cycle time by 14 – 20%, plus reduced the load on the spine by
66%.

The graph
below compares lifting a series of eight boxes onto the conveyor,
first with the pallet on the floor and then with the pallet lift. The
sequence and orientation of the boxes were exactly the same. The only
difference is the height. The results are superimposed to help
highlight the differences.
Each peak
represents one lift. The lower the peak and the less area in the
peak, the less strain on the back. The less horizontal distance at
the base of each peak, the less time needed to make the lift.

The visual
display of the graph clearly shows the benefits of the pallet lift and
raising the boxes off the floor:
-
The peaks
are lower, indicating less risk of injury
-
The area
of the graph is less, also indicating less risk of injury
-
The time
to perform the task is less, specifically eight trays are lifted
using the pallet lift in the time it normally takes to lift seven.
Quantitative evaluation shows that the average load on the spine for
these eight lifts without the pallet lift was 494.7 lbs. and with the
pallet lift 166.1 lbs. Thus, the load on the spine was 66.1% less.
The time
needed to complete these eight lifts was reduced from 25.5 seconds to
22.0 seconds, thus a savings of 13.7%. Additionally, a time study was
performed on a full pallet-load of trays, which yielded a slightly
larger time savings. The time needed to unload a full pallet of trays
was about 6.5 minutes without the lift and about 5.2 minutes with the
lift, thus a savings of about 20%.
Example 3: Resolving a
Labor-Management Dispute
This
example is from a company that inspects and repairs bags and other
small containers for a major distribution company. The union had
complained that the work was too fast and should be slowed down.
Management claimed that slowing down the work economically unfeasible.

This task
involved two parts: inspecting and stacking the containers (A in the
graph above), then straightening and reorienting the stack and
carrying it to a pallet on the floor (B above). The argument had been
about the time it took to perform step A. However, the analysis
clearly showed that part B was the demanding activity that was causing
the exertion and fatigue.
Moreover,
it was possible to eliminate all of part B by purchasing a pallet lift
and stacking the containers directly onto the pallet. This made about
one-third more time available, both for more rest and for more
production. Thus more containers could be inspected with less effort
and resulted in a win-win solution.
Caveat — “Safe” Limit
As a final
note, I generally do not use this method — or any method — to
determine if a job is “safe” or not. I’m generally more interested in
looking for ways to improve any job, since even if a particular
situation has low risks for injury, there may still be inexpensive
ways to make it more efficient and easier to do. Furthermore, the
scientific studies haven’t yet identified “safe” levels for loads on
the shoulders, elbows, or wrists (although such evidence exists for
the lower back).
However,
this method may end up being a good tool for this purpose. It
provides a good way to capture a lot of information on the physical
demands of specific tasks, which then can be compared to numbers of
injuries associated with those tasks to help find out what is
in fact “safe” and “unsafe.”
A good
general rule for practical ergonomics is to play down measurement
systems. If the goal is to solve problems, rather than merely
documenting them, it is much more valuable to get in the habit of
simply watching videos of jobs and focusing on brainstorming
improvements.
However,
from time to time, you may need to quantify the physical demands of a
task. Numbers have power and you may need them to convince
others of the need to take action. Furthermore, sometimes the
problems aren’t so obvious and you can benefit from a closer, more
detailed look.